Testing Procedure
This section is designed to be utilized by a experienced
installer or electrical contractor who has prior experience with
installation of the RE-4500 and is to provide an installation
procedure checklist to insure that the Inverter has been
installed properly.
Perform the following checks before continuing:
1.
Mount the inverter properly mounted with sufficient
ventilation.
2.
DC cables have been connected to the inverter (but
disabled by the DC disconnects).
3.
AC wiring has been completed (but has been disabled by
the AC disconnects).
4.
All connections have been checked.
Start-up and Testing procedure can now be performed.
Warning
These procedures are to be performed only by a QUALIFIED
INSTALLER.
Inverter Start-up and Testing
1.
Place the Inverter ON/OFF switch in the OFF position.
2.
Verify that any external AC output circuit breakers are
reset.
3.
Make certain that the DC and AC sources to the inverter
are all disconnected from the inverter via the code required
disconnects.
4.
Verify that the DC power leads are connected properly to
the inverter in the DC raceway.
5.
Verify that the AC load and Utility leads are connected to
the proper terminals in the AC raceway.
6.
Reconnect the DC source via the code required disconnect
to the Inverter.
7.
With a Voltmeter, verify that the proper input voltage (24
or 48 volts) is present at the Inverter DC IN terminals.